Payal Chawla 
Columns

Navigating Commercial Disputes: Key to Enforcing Liquidated Damages

The enforcement of liquidated damages necessitates meticulous drafting of the contractual clause and precise articulation in pleadings.

Payal Chawla

There is a stark contrast between the legal principles surrounding liquidated damages and how these clauses are often drafted in practice. This disconnect highlights a divergence between those responsible for crafting contract terms and those who must defend them in court.

The enforcement of liquidated damages necessitates meticulous drafting of the contractual clause and precise articulation in pleadings. Both aspects are indispensable and must work in tandem. The omission of essential elements may undermine the very purpose of incorporating a liquidated damages provision.

On the other hand, a well-drafted liquidated damages clause in a contract and the corresponding pleadings can significantly improve the likelihood of securing liquidated damages, thereby expediting dispute resolution and minimizing the duration and costs of protracted litigation. Furthermore, well drafted enforceable  clauses alleviate the burden on courts, contributing to a more efficient judicial process.

Construction of the Contract

A liquidated damages clause must meet certain essential requirements to ensure its validity and enforceability. The mere presence of a liquidated damages clause does not automatically ensure the grant of liquidated damages. The clause should represent a genuine pre-estimate of the potential loss likely to arise from a breach and ideally specify that the amount is calculated based on a reasoned assessment of possible damages. In ONGC Ltd. v. Saw Pipes Ltd., it was emphasized that reasonable compensation may be awarded even in the absence of proof of actual loss, provided it does not constitute a penalty or appear excessive, particularly when explicitly stipulated in the contract. While terminology such as "penalty" is not conclusive, it can influence the interpretation of the clause and potentially undermine the award of damages. Therefore, its use is best avoided.

The damages stipulated must bear a reasonable correlation to the alleged breach. A lack of such correlation may result in the clause being deemed a penalty rather than liquidated damages (Ghaziabad Development Authority v. Union of India). For high-value contracts, involving experts such as technical consultants or damages analysts at the drafting stage can help assess potential breaches and quantify damages. Detailed documentation of the rationale, calculations, and negotiations underpinning the clause is critical; the greater the detail and correlation to the breach, the stronger the likelihood of the damages being upheld.

The clause should clearly specify the nature of breaches it covers and outline the method for determining damages. In State of Karnataka v. Shree Rameshwara Rice Mills, the Supreme Court further clarified that the power to assess damages is subsidiary to the primary issue of adjudicating a breach. Explicitly stating that actual losses would be difficult to ascertain strengthens its enforceability. Moreover, the clause's primary purpose must be compensatory rather than punitive. As noted in Chitty on Contracts, assessing the clause's predominant intent at the time of drafting is pivotal in determining its validity.

A well-drafted liquidated damages clause must be fair, defensible, and grounded in realistic pre-estimates of loss. It should be precise, and designed to reflect a compensatory intent. Without these elements, the clause risks being invalidated as a penalty.

Importance of succinct pleadings

Precise pleadings are critical to successfully claiming liquidated damages, as emphasized in several landmark judgments.

In Fateh Chand v. Balkishan Dass, the Supreme Court rejected the High Court's interpretation that a forfeiture clause automatically equated to a deposit for due performance. The Court underscored that such a conclusion requires specific pleading and supporting evidence.

In Sudershan Kumar Bhayana v. Vinod Seth, a Division Bench of the Delhi High Court outlined three essential elements that a party seeking damages must plead and prove: (1) the counterparty has breached the contract, (2) the claiming party has suffered injury as a result of the breach, and (3) the harm suffered was a direct and proximate consequence of the breach. Additionally, it must be pleaded that the stipulated damages represent a genuine pre-estimate of the likely loss. The claimant must either provide proof of the loss incurred or assert that the loss is inherently incapable of precise quantification.

Several cases have upheld liquidated damages clauses as genuine pre-estimates of loss, particularly in situations where the loss is difficult to quantify. Notable examples include Forbes Gokak Ltd. v. Central Warehousing Corp. and Belco Enterprises v. DTC. Such damages are enforceable without proving actual loss, provided the pre-estimate is reasonable and the loss is difficult to quantify (ONGC Ltd. v. Saw Pipes Ltd.). In such cases, the burden of proof is on the breaching party to show that no loss was caused due to the breach (Construction and Design Services v. DDA). Recently, the Delhi High Court upheld an arbitral award applying this principle in Quadrant Televentures Ltd. v. ATC Telecom.

The Bombay High Court, in Hindustan Petroleum Corporation Ltd. v. Offshore Infrastructure Ltd., reaffirmed the principle laid down in Kailash Nath Associates v. Delhi Development Authority that unless a loss is both pleaded and proven, where it is capable of being quantified, it cannot be recovered. Section 74 of the Indian Contract Act entitles the aggrieved party to reasonable compensation without the need to prove actual loss, provided the amount is neither arbitrary nor excessive. However, in the absence of any legal injury or loss, no compensation can be claimed (Fateh Chand v. Balkishan Dass). There can be no unjust enrichment or "windfall" for a party to claim liquidated damages if no actual loss is suffered or proven (Kailash Nath (Supra)). However, in cases where damages are difficult to quantify, the stipulated amount may be accepted as a "rough and ready measure" of compensation, provided it reflects a genuine attempt to pre-estimate the potential loss (Chitty on Contracts).

As the Supreme Court in BSNL v. Motorola aptly noted, “Liquidated damages serve the useful purpose of avoiding litigation and promoting commercial certainty”. Thus, careful drafting of contract and pleadings not only enhances enforceability but also minimizes prolonged disputes.

Payal Chawla is the founder of JusContractus, a Delhi based full-service law firm, with the primary focus on arbitrations.

The author recognises the assistance of Aastha Bhardwaj, Principal Associate, Inventus Law Technology Partners.

Delhi High Court blames accused on bail for delaying Delhi riots trial, finds no fault with police or court

NCLT can examine fraud in oppression and mismanagement cases: Supreme Court

Collegium recommends 26 new judges to Allahabad High Court including Supreme Court lawyers Garima Prashad, Swarupama Chaturvedi

Supreme Court paves way for ISL 2025-26 to kick-off in December; directs AIFF to stick to calendar

Hurried trial detrimental to accused also: Delhi High Court in order denying bail to Sharjeel Imam, Umar Khalid

SCROLL FOR NEXT